November 25, 2024 | 22:22 GMT +7

  • Click to copy
Tuesday- 21:36, 04/07/2023

Success and lessons learned in the irrigation sector

The disbursement rate will exceed 99 percent

(VAN) According to World Bank experts, the disbursement rate is a positive sign, particularly in light of the fact that several new regulations have been issued that hinder administration and operation.

Excellent execution of the components within the WB8 project

Vietnam Dam Rehabilitation and Safety Improvement Project (WB8) is funded by the World Bank (WB) between 2016 and 2023. The project seeks to improve the safety of specific dams as part of the Government's Dam Safety Program in order to protect downstream communities and economic activities through prioritizing investments and enhancing the capacity to protect residents and socioeconomic infrastructure in lowlands. After deductions, the total investment for the undertaking reached USD 337 million, which included USD 28 million of domestic reciprocal capital.

WB8 project at Dong Man lake, Luc Ngan district, Bac Giang province. Photo: Minh Phuc.

WB8 project at Dong Man lake, Luc Ngan district, Bac Giang province. Photo: Minh Phuc.

The total number of authorized lakes on the list is 475, of which 463 are under construction and 39 are not yet under construction. As a result of the World Bank's agreement to extend the project until June 30, 2023, six months earlier than originally planned, ODA capital will no longer be used to fund its construction.

The Ministry of Agriculture and Rural Development issued a decision on May 8, 2023, authorizing the adjustment of 436 lakes to the list of lakes for construction. To date, 409 lakes out of a total of 436 that have been begun have been completed, while 27 are still under construction. Up to 26 of the 27 lakes under construction have completed over 80% of their work. Only the Tha Lake in Hoa Binh has a significant amount of unresolved construction.

According to the WB8 Project Management Board, following the completion of the project, the Board will urge the eight provinces of Phu Tho, Hoa Binh, Hai Duong, Thanh Hoa, Ha Tinh, Quang Nam, Phu Yen, and Dak Lak to construct the remaining 27 lakes.

Thai Nguyen, Phu Tho, Thanh Hoa, Quang Ngai, and Dak Nong must secure sufficient ODA for allocation and re-lending. In addition, the WB8 Project Management Board will continue to coordinate with relevant units, finalize the adjustment of the project's capital structure, and cancel the excess capital for the unfulfilled activities; implement project completion reports; and finalize procedures for closing ODA-funded projects.

The rate of disbursement exceeds expectations

Mr. Ahmed Eiweida, Vietnam Sector Leader for Sustainable Development (WB), stated during the summarizing session of the Inspection team evaluating the project that the WB8 project is a protracted voyage involving WB, MARD, and 33 localities.

Summary meeting of the Monitoring and Evaluation Team of the Dam Safety Improvement and Repair (WB8) project. Photo: Quang Linh.

Summary meeting of the Monitoring and Evaluation Team of the Dam Safety Improvement and Repair (WB8) project. Photo: Quang Linh.

Due to the efforts of all parties involved, the project has yielded numerous positive outcomes, particularly in preventing dam-related hazards to human life and socioeconomic factors.

Mr. Ahmed Eiweida expects the restructured project to disburse between 98 and 99 percent of the total capital allocated. The World Bank loan has been disbursed in the amount of USD 274 million, which is equivalent to 83 percent of the project's total capital.

Mr. Pham Hung Cuong, senior irrigation expert of the World Bank. Photo: Minh Phuc.

Mr. Pham Hung Cuong, senior irrigation expert of the World Bank. Photo: Minh Phuc.

Pham Hung Cuong, a senior irrigation expert at the World Bank, stated that as of the 15th of June, 83% of the USD 273 million allocated to the project had been disbursed. On June 30th, the majority of investments in the construction, maintenance, and improvement of reservoirs and dams were completed or concluded.

Deputy Minister Nguyen Hoang Hiep estimated that the project's implementation will take 7 years in 33 provinces and cities, with 90% of its budget allocated to minor initiatives and subcomponents. Due to the project's complexity and scope, MARD deemed it to be excellently completed.

Deputy Minister of Agriculture and Rural Development Nguyen Hoang Hiep assessed the implementation of the WB8 project. Photo: Quang Linh.

Deputy Minister of Agriculture and Rural Development Nguyen Hoang Hiep assessed the implementation of the WB8 project. Photo: Quang Linh.

Notably, according to the WB8 initiative Management Board's report, 2,9 million persons directly benefit from the initiative, including 1,4 million women (7.4% more than anticipated). In addition, direct benefits from the downstream area reached an additional 5.06 million people (23.3% more than planned), including 2.47 million women (17.5% more than planned).

The consulting services include the following deliverables: Environmental safety report; dam safety report; feasibility research report; environmental impact assessment report; construction protection design; safety policy screening; dam safety report. All social security reports are submitted on time or ahead of schedule.

Deputy Minister Nguyen Hoang Hiep proposed that the Central Management Board of Irrigation Projects, the Department of International Cooperation, and the Department of Irrigation coordinate with related parties to swiftly adjust the overall investment policy of the project so that the provinces are reciprocal capital contributors.

The deputy minister also requested that, if 27 lakes currently under construction are not completed by June 30, local governments will begin actively arranging funds to complete the project on July 1.

The project comprises three components:

Component 1: Rehabilitation of dam safety - This component will enhance dam safety by rehabilitating existing infrastructure. This would include assistance with (i) detailed design, supervision, and quality control of rehabilitation works for prioritized dams and associated infrastructure; (ii) rehabilitation works, including civil works, hydro-mechanical works, and installation of hydrological and safety monitoring equipment; (iii) preparation of Operation and Maintenance Plans and three Emergency Preparedness Plans; and (iv) adoption of a standard checklist for community-managed dams.

Component 2: Dam safety management and planning - This component will enhance the planning and operational framework for dam management in order to protect downstream communities' people and socioeconomic infrastructure. This would include support for: (i) hydrological observation networks and information systems; (ii) integrated development planning; (iii) regulatory and institutional support; (iv) technical specifications, safety standards, and regulations at internationally-acceptable levels; and (v) capacity enhancement.

Component 3: Project management assistance - This component will provide the essential environment to facilitate the implementation of the project. Support will be provided for the following: (i) Project Steering Committee; (ii) Central Project Management Unit (CPMU); (iii) Technical Assistance for beneficiary departments; (iv) Establishment and operations of a National Dam Safety Review Panel; (v) Independent audits of prioritized dams before and after rehabilitation; and (vi) Incremental operating costs for project-related activities.

Authors: Quang Linh - Minh Phuc

Translated by Linh Linh

Funds facilitate West Africa rice production

Funds facilitate West Africa rice production

(VAN) The project’s goal is to increase food security and sovereignty by encouraging public and private investments in rice value chains to increase self-sufficiency in rice by 2030 in West Africa.

Restoring the ecosystem of Tram Chim National Park: Bringing the crane flock back

Restoring the ecosystem of Tram Chim National Park: Bringing the crane flock back

(VAN) One of the outstanding efforts of Dong Thap province in restoring and preserving the ecosystem of Tram Chim National Park is the project to bring the crane flock back to Tram Chim National Park.

Restoring the ecosystem of Tram Chim National Park: Five core contents in management and conservation

Restoring the ecosystem of Tram Chim National Park: Five core contents in management and conservation

(VAN) In order to make the management and conservation of the ecosystem in Tram Chim National Park more effective, there are the five most core contents that must be focused on.

Restoring the ecosystem of Tram Chim National Park: A wetland with diverse and rich ecosystem

Restoring the ecosystem of Tram Chim National Park: A wetland with diverse and rich ecosystem

(VAN) With the role and biodiversity value of Tram Chim National Park, the government of Dong Thap province paid special attention to investing in managing and preserving the Park's ecosystem.

Opportunity for Son La to produce high-tech agriculture

Opportunity for Son La to produce high-tech agriculture

(VAN) With over 210,000 hectares of cultivated land, Son La province has just over 51 hectares of vegetables grown in high-tech greenhouses, accounting for a mere 0.02% of the total area.

Genetic clues could help breed chickens resilient to bird flu

Genetic clues could help breed chickens resilient to bird flu

(VAN) Several areas of chickens’ DNA may influence natural resistance against bird flu, according to research.

Ukrainian poultry farmer reveals plan of huge investments in Slovakia

Ukrainian poultry farmer reveals plan of huge investments in Slovakia

(VAN) EU Poultry, a Slovak poultry processor owned by Ukrainian businessman Dmytro Borodavka, has rolled out plans to invest almost €50 million into capacity expansion in the country.

Read more