Landslides and flood tides are two types of existing natural disasters in Can Tho City in 2023. In May 2023 alone, Can Tho City recorded three consecutive serious landslides occurring in Thoi Lai district and Binh Thuy district.
Currently, the Can Tho Department of Agriculture and Rural Development is strengthening solutions to inspect and review the area of riverbanks and canals at the beginning of the rainy and stormy season in 2023. At the same time, the unit also has plans to mobilize and relocate people in landslide-risk areas and build temporary and biological embankments to minimize the occurrence of landslides.
At the landslide point in Thoi Thuan area, Thoi An Dong ward, Binh Thuy district, which occurred on May 19, the traffic route, along Tra Noc river and about 320m from Tra Noc 2 bridge towards KH8 canal, collapsed into the river and was completely dismembered. The length of the landslide section is about 50m; the length of the landslide-risk section is 50 m; and the depth of the landslide point is about 5m.
Binh Thuy district government has implemented a ban on the 1T load sign and the notice board "area at risk of riverbank landslide" to warn, manage traffic and boats anchored to the above locations, and at the same time limit the impact on the work.
Recently, the Binh Thuy People's Committee has written to the Can Tho People's Committee to have a plan to support and overcome the above-mentioned landslide point by building a solid concrete embankment, ensuring life, property, and traffic for people. Besides, the landslide point is showing signs of encroaching on the shore, threatening the safety of people and the houses of households living inside the route.
In recent years, the landslide situation in Can Tho City in particular and the Mekong Delta in general has become alarming, not only in the rainy and stormy season but also in the dry season.
In Thoi Lai district, within four days, two landslides occurred in Tan Thanh commune. Specifically, on May 20, the 55-meter road along the banks of the O Mon river in Thoi Phuoc 1 hamlet suddenly collapsed and attacked 8m deep into the bank, risking further landslides about 50m long. On May 24, Thoi Khanh hamlet also recorded a 40-meter road landslide.
In addition to planning to overcome the consequences of landslides, the Thoi Lai People's Committee has proposed that the Can Tho People's Committee develop an investment plan to respond to landslides according to the path at 13 points located on the O Mon River section with a length of over 7km that currently have very high potential for landslides.
Recently, during a field trip to survey landslide points, Mr. Nguyen Ngoc He, Vice Chairman of the Can Tho People's Committee, asked relevant authorities to review the entire riverbed depth at the landslide-occurring points. From there, plan emergency solutions to overcome the problem, which can include the construction of a bridge or a solid embankment to ensure stable lives in the affected area.
According to the Can Tho Department of Agriculture and Rural Development, from 2010 to 2022, the city had 262 landslides with a total length of approximately 10,000 m, and 94 houses were completely damaged. The landslide also left four people dead and five injured. At present, the evolution of riverbank and canal landslides in the city is still complicated and unexpected, especially in areas with high traffic density and river sections located at the intersection between river flows and tides, etc.
In order to increase the resilience of Can Tho city to the risk of flooding and improve urban management capacity to adapt to climate change, since June 2016, the city has launched the Project on Can Tho City Development and Enhancing Urban Adaptability. The project is funded by the World Bank (WB) and aims to strengthen the capacity of the Can Tho city government in disaster risk management.
On May 25, Mr. Tran Viet Truong, Chairman of the Can Tho People's Committee, had a field trip to check the construction progress of some works under the above-mentioned project, such as the tender package to renovate drainage systems in the center of Ninh Kieu district and the tender package for the construction of Tran Hoang Na bridge.
According to the ODA Project Management Board (under the Can Tho People's Committee), the tender package CT3-PW-1.11: Renovating drainage system in the center of Ninh Kieu district will be implemented on 34 roads across the district. Currently, the construction progress of the completed culverts reaches about 65% of the work volume. With the package CT3-PW-2.4: Construction of Tran Hoang Na Bridge, which started from September 2020 until now, the workload has reached over 77%.
Regarding the Cai Son embankment project, Mr. Tran Viet Truong suggested that the Ninh Kieu People's Committee must ensure the handover of the site to the construction unit in June to ensure the schedule. This is a project that is expected to effectively solve the landslide problem for the section from Cai Son bridge, An Binh ward, Ninh Kieu district, to the point adjacent to the anti-landslide embankment project in My Khanh market area, Phong Dien district.
With a large remaining workload and the current slow construction progress, Mr. Tran Viet Truong asked the ODA Project Management Board, contractors, and construction units to speed up the progress, focus force on it, and report difficulty to find solutions.
In particular, quickly solve problems related to materials and unify construction methods for the remaining work items to avoid prolonging them. During the construction process, the units must pay attention to ensuring absolute labor safety, proper construction techniques, and strict documentation in accordance with the process.
Chairman Tran Viet Truong suggested that all of the above work items be completed before September 2, 2023, ensuring benefits for people and convenience for travel, trade, and activities during the rainy and stormy season in 2023 and improving the capacity of Can Tho city to cope with climate change.
Translated by Huyen Vu Thu
(VAN) An Giang has over 300,000 farmers directly engaged in rice production and 229 cooperatives playing a pivotal role in the implementation of the One Million Hectares of High-Quality Rice Project.
(VAN) C.P. Vietnam continues to accompany Dong Thap province to build green embankments to protect land and prevent landslides on river banks in 12 districts and cities.
(VAN) The Quang Tri Department of Agriculture and Rural Development collaborates to pilot the Greenhouse Gas Emission Reduction Project in agriculture.
(VAN) Positive results in mass vaccination against African swine fever in Vietnam will become important evaluation bases for other countries.
(VAN) Ha Long Bay's 30-year journey as a recognized world natural heritage site is reflected through the numerous achievements in promoting its heritage's values.
(VAN) 'The agricultural sector is restoring soil nutrients. The fisheries industry has also begun to think about restoring the farming environment,' said Director Tran Dinh Luan.
(VAN) With a passion for sustainable agriculture, many agricultural cooperatives in Tuyen Quang have cultivated long-term farms, thereby establishing strong brand value in the market.