Canh Tang Reservoir Project: Over budget, behind schedule due to the fault of the locality

(VAN) Regarding responsibility for compensation and resettlement of Canh Tang Reservoir Project, Mr. Bui Van Khanh, Chairman of the Provincial People's Committee of Hoa Binh province, said: 'This is the fault of the locality'.
Deputy Minister Nguyen Hoang Hiep (right site) and Mr. Bui Van Khanh - Chairman of the Provincial People's Committee of Hoa Binh province, survey the construction site of Canh Tang reservoir. Photo: Minh Phuc.

Deputy Minister Nguyen Hoang Hiep (right site) and Mr. Bui Van Khanh - Chairman of the Provincial People's Committee of Hoa Binh province, survey the construction site of Canh Tang reservoir. Photo: Minh Phuc.

On the morning of March 29, Deputy Minister of Agriculture and Rural Development Nguyen Hoang Hiep had a meeting with Hoa Binh province to discuss solutions to overcome difficulties and obstacles in implementing the Compensation, Support and Resettlement Component of Canh Tang Reservoir project (Hoa Binh province).

According to Lac Son District People's Committee, the review results show that the total investment to complete the compensation and resettlement component of the project is VND 1,533 billion (an increase of VND 474 billion compared to the original approved plan). The reason is due to the cost of afforestation, construction costs increase. The inundation landmarks of the lake bed do not fully represent the flooded area and affected properties. Therefore, it is necessary to review additional measurements, increase the volume of ground clearance and increase the budget for site clearance...

According to the report, the total land acquisition and clearance area for project implementation are 897.4 hectares (down more than 340 hectares compared to the approved plan). The total number of households and individuals affected by the construction of the works is 596 households. Of which 574 households had to relocate to new places of residence, the remaining 22 households resettled themselves.

Regarding housing compensation, up to now, the compensation plan for house clearance has been approved for 574 households in Yen Phu, Van Nghia, Binh Alle communes and is currently paying compensation to households. However, the locality still does not have the funds to pay for 106 households (VND 25.1 billion).

At some resettlement sites, many households have finished building their houses. But, because the items of rainwater drainage, wastewater drainage, and concrete pavement have not been constructed yet, the households have not been able to move to stay.

In addition, many households have houses and assets located within the construction area of the flood avoidance route (this is the main road leading to the construction of resettlement sites) due to the lack of space to build houses at resettlement sites, so they can't move right away.

The Delegate of the Ministry of Agriculture and Rural Development inspected the Canh Tang reservoir project. Photo: Minh Phuc.

The Delegate of the Ministry of Agriculture and Rural Development inspected the Canh Tang reservoir project. Photo: Minh Phuc.

Deputy Minister Nguyen Hoang Hiep emphasized that Canh Tang Reservoir project has a total investment capital of more than VND 3,118 billion. The construction component (VND 890 billion) is invested by Irrigation Construction Investment Management Board 1 ('Board 1'). The site clearance component is more than VND 1,100 billion funded by Hoa Binh province. The water channel component of more than VND 1,100 billion, the Provincial People's Council of Hoa Binh province commits to invest when the Ministry of Agriculture and Rural Development completes the construction of the reservoir...

The main project construction component that the Ministry of Agriculture and Rural Development directly directed Board 1 to be the investor has been completed, and there is not much construction remaining. But the problem is that we can't block the flow. We can't store water because we haven't cleared the surface of the lake bed.

"Consultants are very problematic. Because when clearing the site, the consultant must know what to do first and what to do later. However, the two roads leading to the resettlement area did not work first but instead made the resettlement area. How can people live here?", Deputy Minister Nguyen Hoang Hiep said.

Regarding the local responsibilities in implementing the Compensation and Resettlement Component of the Canh Tang reservoir project, Mr. Bui Van Khanh - Chairman of the Provincial People's Committee of Hoa Binh province, admitted: "This is the fault of the locality. ".

The project has been implemented for four years, and the volume of construction and installation has been completed 70%, but the construction and site clearance does not go balanced.

Through preliminary analysis of the cause, in the end, it was because the consulting unit determined the number of families to move, the number of land assets to be compensated was incorrect at first, leading to an increase in the amount of compensation compared to the initial project approval. Regarding allocating additional capital to implement Canh Tang reservoir project's site clearance and resettlement component, the People's Committee of Hoa Binh province will report to the Deputy Prime Minister and Prime Minister for consideration and direction.

Author: Minh Phuc

Translated by Ha Phuc

Approval of the biotechnology project in the field of environmental protection

Approval of the biotechnology project in the field of environmental protection

(VAN) On December 24, Deputy Prime Minister Tran Hong Ha signed Decision No. 1639/QĐ-TTg approving the project on the development of biotechnology in the field of environmental protection.

Vietnam's tea exports earned nearly 235 million USD in 11 months

Vietnam's tea exports earned nearly 235 million USD in 11 months

(VAN) Vietnam's tea exports to key markets in the first 11 months of 2024 saw significant increases compared to the corresponding period in 2023.

New grain terminal opens in Saudi Arabia

New grain terminal opens in Saudi Arabia

(VAN) National Grain Co., a joint venture between the Saudi Agricultural and Livestock Investment Co. (SALIC) and Bahri, inaugurated the Yanbu Grain Handling Terminal on Dec. 22 at Yanbu Commercial Port.

Major agricultural innovation could change how all food is grown

Major agricultural innovation could change how all food is grown

(VAN) Agrivoltaics combines solar energy and agriculture, enhancing land productivity and addressing climate change while ensuring food security.

How is China achieving record harvests despite reducing fertiliser use?

How is China achieving record harvests despite reducing fertiliser use?

(VAN) China has reduced fertiliser use for eight consecutive years since 2015 and yet the country's agricultural output has steadily increased with 2024 grain production hitting a historic high.

The controversial machine sending CO2 to the ocean and making hydrogen

The controversial machine sending CO2 to the ocean and making hydrogen

(VAN) Equatic is among a wave of start-ups exploring how the ocean could be harnessed to capture and store carbon. But not everyone is sure it's such a good idea.

The one million hectares of high-quality rice project: a major revolution

The one million hectares of high-quality rice project: a major revolution

(VAN) An Giang has over 300,000 farmers directly engaged in rice production and 229 cooperatives playing a pivotal role in the implementation of the One Million Hectares of High-Quality Rice Project.

Read more